Promoter's Statutory Obligation to Refund Allottee Amounts Under Section 18 RERA Is Absolute

Highlights of the Judgment:
- Examination of whether a promoter's obligation to refund amounts under Section 18(1) of the RERA Act is absolute and unqualified.
- Differentiation between obiter dicta and ratio decidendi concerning Supreme Court observations in Newtech Promoters.
- Analysis of the regulatory authority's lack of discretion to delay refunds until obtaining an occupation certificate.
- Reconciliation of conflicting interpretations regarding mitigating circumstances for project delays under RERA.
- Distinction between statutory refund obligations and separate adjudicatory mechanisms for compensation claims.